RES NO 09-05-2002 CITY OF VAN BUREN, ARKANSAS
0 RESOLUTION NO. e t 5 -2002
A RESOLUTION APPROVING AN INCREASE IN THE CONTRACT PRICE FOR THE
SHERWOOD STREET PROJECT.
WHEREAS, The Mayor has advertised for bids for the Sherwood Street Project; and
WHEREAS, The bid of Harris Company in the amount of $113,977.14 was accepted by
the Council; and
WHEREAS, Due to unforeseen circumstances, the amount to complete the street
improvements has increased;
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF VAN BUREN,
ARKANSAS:
SECTION 1: That the increase of $4,005.96 to the Contract with Harris Company for
street improvements is hereby accepted.
SECTION 2: That the Mayor is authorized and directed to pay for same out of the
Street Fund.
PASSED AND APPROVED THIS 16-4 DAY OF SEPTEMBER, 2002.
1
MAYO J O IN RIC
ATTESTED:
Ce*A -AX 4
CITY CLERKITRE'
0
Project: 2002 Street Improvements /Sherwood Street
0 Contractor: Harris Company of Fort Smith, Inc.
Change Order No. 1
Date: 9/9/02
Project Contract
Item No. Quantity Unit Description Unit Cost Amount
1 1 LS Site Preparation $32,875.00 $32,875.00
2 103 SY Remove Replace 6" Concrete Driveway $35.00 $3,605.00
3 263 SY Concrete Sidewalk (5' wide) $12.90 $3,392.70
4 840 LF Concrete Curb Gutter $10.00 $8,400.00
5 6 EA Furnish Install 5'x5' Side Inlet $1,700.00 $10,200.00
6 1 EA Furnish Install 5'x7' Side Inlet $2,000.00 $2,000.00
7 386 LF 14 "x22" RCPA $34.00 $13,124.00
8 85 LF 11 "x18" RCPA $30.84 $2,621.40
9 1 EA 115(18" RC Flared -end Section $500.00 $500.00
10 0 SY Grade Compact Subgrade $5.98 $0.00
11 795 TONS Furnish Install Class 7 Crushed Stone Base $13.50 $10,732.50
12 200 TONS Furnish Install Class 2 Asphalt Concrete Pavement $60.00 $12,000.00
13 0 LF Furnish Install 4" Underdrain $9.00 $0.00
14 300 SY Furnish Install Bermuda Sod $2.00 $600.00
15 0 EA Remove Relocate Fire Hydrant $1,000.00 $0.00
16 715 TONS Undercut Replace w/ "B" Stone $15.50 $11,082.50
17 120 SY Cold Mill Asphalt $16.00 $1,920.00
18 10 SY PC Base $20.00 $200.00
19 1440 SY Remove Dispose Asphalt Paving $2.00 $2,880.00
20 125 CY Unclassified Excavation $10.00 $1,250.00
21 1 LS Seed Mulch Disturbed Area $600.00 $600.00
Totals $117,983.10
Current Contract Amount $113,977.14
Change Order No. 1 Amount $4,005.96