RES NO 08-05-1989 g -s- €189
CITY OF VAN BUREN, ARKANSAS
RESOLUTION NO. 5 8 -1989
A RESOLUTION ACCEPTING THE ALTERNATE BID OF FORSGREN, INC.
FOR REBUILDING AND OVERLAY OF RUDY ROAD FROM I -40 OVERPASS TO EAST
CITY LIMITS.
WHEREAS, The Mayor has advertised for bids for overlay
and rebuilding of Rudy Road from I -40 Overpass
to East City Limits; and
WHEREAS, The attached bids have been received; and
WHEREAS, The Council feels that the Alternate Bid of
$95,777.00 of Forsgren, Inc. is the best
bid:
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF VAN BUREN, ARKANSAS:
THAT, The Alternate Bid of $95,777.00 of Forsgren,
Inc. is accepted.
THAT, The Mayor is authorized and directed to pay for
same out of Capital Improvements Fund.
PASSED AND APPROVED THIS 28TH DAY OF AUGUST 19 89
Gl LN"1
MAYO
ATTESTED:
A ce A4
CITY CLERK- TREASURER
l
�h� hoffman prieur Et associates, inc.
1.21:LJ land surveyors consulting engineers
Ivan L Hoffman, Jr.,
Alvin L Prieur, Jr.. P.E.
Mork). &een, P.LS.
August 28, 1989
0
City of Van Buren
City Hall
Van Buren, Arkansas 72956
Attn: The Honorable Robert E. "Gene" Bell
Mayor, City of Van Buren
RE: Bids Rudy Road Improvements
Van Buren, Arkansas
Dear Mayor Bell:
We have reviewed the bids received today on the above referenced
project. The low "Base Bid" was from Crawford Construction Co. in
the amount of $86,440.30. This is for the work as originally
designed.
The low "Alternate Bid" was from Forsgren, Inc. in the amount of
$95,777.00. This is for an alternate to scarify and recompact the
entire road before the overlay. This option will provide a better
road for the future. A cost overrun could be possible with this
alternate if problems are found during scarification of the existing
pavement surface.
We would recommend that the "Alternate Bid" in the amount of
$95,777.00 be accepted and the contract awarded to Forsgren, Inc.
If you have any questions, please contact me.
I do plan on being at the council meeting tonight, if any questions
arise during the meeting.
I would recommend that we return the bond (cashier's check) from
Tarkington Construction.
Sincerely,
HOFF PRIEUR ASSOCIATES, INC.
Alvin L. Prieur, Jr., P.E.
ALP /kh
(501) 474 -7916 p.o. box 1226 von buren, orkonsas 72956
i s
hoffman prieur associates, inc.
land surveyors consuldng engineers
Ivan L Hoffman. Jr., P.LS.
Alvin L Prleur. Jr., P.E.
Mork J. Breen, P.LS.
BID SUMMARY
Street Reconstruction
Rudy Road Improvements
Van Buren, Arkansas
Bid: 10:00 a.m.
August 28, 1989
BIDDER BOND BASE BID ALTERNATE BID
Crawford Const. Associated
Fort Smith, AR Indemnity $86,440.30 $98,845.50
Corp. 5%
Forsgren, Inc. James
Fort Smith, AR 5% $89,401.00 $95,777.00
JOB Const. Mid- Contient
Poteau, OK 50 $99,733.10 $114,691.00
Tarkington Const. $5000.00
Fort Smith, AR Cashier's $91,808.52 $99,912.60
Check
Engineers Estimate $91,500.00 $103,000.00